2009' CONSTRUCTION RECORDS
no Construction Period Volume Contract Content
Water Tight Door Electric Cable Station #6 2009.06.08 1 SET MOONWHOA CO. Kepco- Daegu Dongseong-ro Project
Blast Proof Door(10 Psi) 2009.06.15 1 SET Dongsung Corp. S-oil
Blast Proof Door (6.5 Psi) 2009.06.18 11 SETS Jinnam Construction Co.,Ltd. GS Caltex Corporation
Water Tight Door Electric Cable Station #3 2009.07.20 1 SET MOONWHOA CO. Kepco- Daegu Dongseong-ro Project
2HR Fire Rated & Bullet Resistant Door 2009.07.30 1 SET DAWON ID & C GROUP Australian Embassy Seoul
2HR-UL Fire Doors 2009.07.30 8 SETS DAWON ID & CGROUP Australian Embassy Seoul
3HR-UL Fire Rated Egress Personnel Door(1) RH and (1)LH Swing 2009.12.08 2 SETS OAKWELL ENGINEERING LIMITED Project B-FM Phase In Singapore
Blast Rated Doors ? Single Leaf with Man Door Access(522Psi) 2009.12.08 4 SETS OAKWELL ENGINEERING LIMITED Project B-FM Phase In Singapore
UL752 Ballistic Rated-Forced Entry Personnel Door(1) RH and(1) LH swing 2009.12.08 2 SETS OAKWELL ENGINEERING LIMITED Project B-FM Phase In Singapore
Blast Rated Doors-Double Leaf Swing(290Psi) 2009.12.08 1 SET OAKWELL ENGINEERING LIMITED Project B-FM Phase In Singapore
Custom Blast Rated Doors-(CBR) Vertical Acting(363Psi) 2009.12.08 2 SETS OAKWELL ENGINEERING LIMITED Project B-FM Phase In Singapore
Custom Blast Rated Doors - Double Leaf Swing with Man Door Aaccess(160Psi) 2009.12.08 1 SET OAKWELL ENGINEERING LIMITED Project B-FM Phase In Singapore
3HR-UL Fire Doors 2009.12.23 3 SETS THE BON CONSTRUCTION CO.,LTD. RAW MATERIAL & PRODUCT SRTOAGE B/D IN FECC.
Blast & Fire rate door 30 kPa/2HR Fire rate 2009.12.27 13 SETS Supreme Support Services FZE ISAF PROJECTIn Kabul, Afghanistan